EMI NA1 Milestones

Latest additions:
2010-07-13
11:11
MNA1.3 - Technical collaboration procedures with EGI and PRACE are established
EMI-NA1-MS3.
- July 2010.
EMI DCI Collaborations in place

Detailed record - Similar records
2010-07-13
11:10
MNA1.5.3 -Successful completion of the periodic and final reviews
EMI-NA1-MS9.
- April 2013.
MNA1.5.3- Successful Completion of the perdiodic and final reviews

Detailed record - Similar records
2010-07-13
11:10
MNA1.4.3 - Service Level Agreements in place
EMI-NA1-MS6.
- April 2013.
Full text

Detailed record - Similar records
2010-07-13
11:10
MNA1.5.2 -Successful completion of the periodic and final reviews
EMI-NA1-MS8.
- June 2012.
Full text

Detailed record - Similar records
2010-07-13
11:10
MNA1.4.2 - Service Level Agreements in place
EMI-NA1-MS5.
- October 2011.
Service Level Agreements in place - Rev. 1

Detailed record - Similar records
2010-07-13
11:10
MNA1.5.1 -Successful completion of the periodic and final reviews
EMI-NA1-MS7.
- June 2011.
Full text

Detailed record - Similar records
2010-07-13
11:10
MNA1.4.1 - Service Level Agreements in place
EMI-NA1-MS4.
- October 2010.
Full text - Full text

Detailed record - Similar records
2010-07-13
11:10
MNA1.2 - Project management information system and tools
EMI-NA1-MS2.
- May 2010.
EMI Project Management Tools

Detailed record - Similar records
2010-07-13
11:10
MNA1.1 - Project Kick-Off Meeting
EMI-NA1-MS1.
- May 2010.
Full text

Detailed record - Similar records